Saturday, February 25, 2012

We are moving on quickly here

The demand for the homes in Bridlewood Villas is not letting up. But the prices are not holding. The homes in the more desirable areas have been increased $10,000.

We still have 2 abbeys in building 17 which will be completed in April. I am offering the $4000 in free upgrades on either of these homes for another 2 weeks, then I get to pick the cabinets and countertops.

Here is the new update for those of you wanting to know where we are in the construction of your home:

Building 1 -- is painted... Hard surface flooring is going in this week and cabinets are supposed to start by March 1
Building 17 -- Sheet rock is done. Finish carpenter should be here this week to do base and doorframes.
Building 2 -- the lumber has arrived for the framing. We are now about 4 months from completion of this building
Building 6 -- the floor will be poured next week if the weather permits. Then the lumber will be here for the framing.
Building 3 and 18 -- yes -- we are now working on these too. The footings and foundation are all poured. Once the concrete has cured we will see the guys backfilling and the plumbers getting the undergrounds in
Building 5 and 19 are now added to the schedule. they will be started in about 6 weeks if the sales continue to be brisk.


The clubhouse is on the schedule to start March 15. It will be bigger and better than any of our others. Then the fun can begin.

Keep checking back for future updates.