Here it is the end of March already and we have made huge progress here at Bridlewood.

Building 1 is almost done. We will have 2 home owners next week. The landscapers are here getting the sprinklers in and ready for sod and trees.

Building 2 is framed, has the wiring in and the heating and air conditioning rough is going in now.

Building 3 now has a concrete floor and will be ready for framing next

Building 6 is 3/4 the way framed

Building 17 is getting painted, has cabinets ordered. We are about 6 weeks away from completion

Building 18 is almost ready for the concrete floor.

Sales are coming steadly and the best news is that our new residents are getting their homes sold. The real estate market here in the Salt Lake Valley is picking up quickly. The recovery is continuing.

We will have a grandview model by April 30 -- if you are waiting for models -- that is your date to come and see me.

Friday, March 16, 2012

Great day for contractors


Warm weather has made it great for the contractors. It is like a beehive here at Bridlewood Villas.
Building 1 is getting the finishing touches. Countertops next, driveways are being formed. They say we will be ready for the first 2 residents by April 1.
We will have model homes ready by April 30 hopefully
Here is the weekly update:
Building 1 -- countertops are next -- driveway and sidewalks on the south side are being formed. The balance of the rock on the outside is about finished.
Building 17 -- the finish carpenter is doing his thing -- paint is next. I still have all 4 homes in this building for sale. Completion date is May 1. I am offering $2500 off any purchase in that building.
Building 2 -- has our new Windsor Court floor plan. The home is now framed.
Building 6 -- is getting the concrete floor today
Building 3 -- The plumbers are almost done with the underground plumbing
Building 18 -- the Plumbers are just starting to play in the dirt getting the plumbing in
Building 4,5,19,20 -- are now on the schedule to sell.
The clubhouse is in the final stages of engineering -- the hole should be dug in the next month.
As you can see -- we are moving ahead quickly.
Prices have been increased for the homes in the center of the project, but not yet on the outside lots. Come get your choice made now.