Here it is the end of March already and we have made huge progress here at Bridlewood.

Building 1 is almost done. We will have 2 home owners next week. The landscapers are here getting the sprinklers in and ready for sod and trees.

Building 2 is framed, has the wiring in and the heating and air conditioning rough is going in now.

Building 3 now has a concrete floor and will be ready for framing next

Building 6 is 3/4 the way framed

Building 17 is getting painted, has cabinets ordered. We are about 6 weeks away from completion

Building 18 is almost ready for the concrete floor.

Sales are coming steadly and the best news is that our new residents are getting their homes sold. The real estate market here in the Salt Lake Valley is picking up quickly. The recovery is continuing.

We will have a grandview model by April 30 -- if you are waiting for models -- that is your date to come and see me.