Monday, April 30, 2012

WEEKLY CONSTRUCTION UPDATE

CLUBHOUSE HAS FOOTINGS AND FOUNDATION

Yes the clubhouse is now underway.   Footings and Foundations are poured and the underground plumbing etc comes next.

Here is the building update.

1.  Our models are partially decorated and you still get to hike in over the dirt, mud, gravel or whatever happens to be there on that day.   I understand that the asphalt will come this week if we have good weather.  GOOD NEWS  ... we have models     BAD NEWS.... bring your hiking boots to get into them.


Building 17:   Cabinets and some countertops are in.  Still on schedule for completion for May 31.  I still have 2 Abbeys in that building for sale.  since the are so close to being completed, we did not raise the prices on them,.   Still with the upgrades they are $244,300 and  $281,900 (one has the bonus room above the garage.)

Building 2:  Sheetrock is being completed this week

Building 6:  Roof is going on, Electrical and HVAC is getting finished up.

Building 3:  is almost finished framing

Building 18:  is ready to start framing

Buildings 4 and 5:  I see the big trackhoe out there today and the stakes are set.  That means that we will have a hole dug today or tomorrow.


As you can tell, we are building very quickly.  Things are very busy here in this community.  Please be careful as you drive around to sight see (we know you all do it).....   There might be nails on the road and big trucks blocking access.

If you come to the sales office and it is empty, I am on the community somewhere.  Come on in and wait, or come over to building 1 north side where we now have models.  That is most likely where I am.   Thanks